Tirupati-Kalahasti-Naidupeta update: All 6-lanes open except minor work

Tirupati-Kalahasti-Naidupeta update: All 6-lanes open except minor work

There are no diversions onto the old road anymore, it’s only the above lane closures which have pending minor work. End of Tirupati 4lane Bypass to NH16 can now be done easily in 30-40 minutes now.

BHPian adetour recently shared this with other enthusiasts:

Tirupati – Kalahasti – Naidupeta is almost fully 6 laned except for minor works, all bypasses open

  • Naidupeta Trumpet Interchange connecting NH16 and NH71 has opened since a few days directly onto Naidupeta NH71 bypass (it was blocked on 18th Dec with stones)
  • All bypasses like Kalahasti, Yerpadu, Renigunta are fully completed
  • There are 3-4 sections where minor work is pending around Kalahasti and Yerpadu, it should be done soon. In these sections, some have 1 lane closed, some have 2 lanes closed
  • There are no diversions onto the old road anymore, its only the above lane closures which have pending minor work
  • End of Tirupati 4lane Bypass to NH16 can now be done easily in 30-40 minutes now

Pictures from yesterday in Naidupeta to Tirupati direction.

NH16-NH71 Trumpet interchange while coming from Nellore side, now also marked in Google Maps
Tirupati-Kalahasti-Naidupeta update: All 6-lanes open except minor work

Minor pending work on Trumpet interchange

Naidupeta Bypass

Completed 6 lane sections from Naidupeta to Kalahasti

Some minor pending work before Kalahasti Bypass

Pending work section on Kalahasti Bypass

Pending minor work after Kalahasti

Yet to be inaugurated toll between Kalahasti and Yerpadu (the only toll on this section)

Yerpadu Bypass

Start of Renigunta Bypass

End of the 6lane road at KLM Circle, Ellamandayam, before Tirupati 4lane Bypass.